University of Sunshine Coast- Petrie Campus Foundation Building

Dewpoint is proud to have now completed the mechanical component of the new University of Sunshine Coast Petrie Campus Foundation Building, encompassing 3 levels and 16,000sqm of this world class facility.

The Project included Central energy system designed to ultimately serve the entire campus (2.5 MW of cooling which can be expanded to 5 MW to meet future needs)Laboratories including PC2 level spacesThe Stoop area featuring underfloor displacement type air-conditioning, dust extraction to the workshop areas, as well as Medical gases to the Nurse Training spaces

It was officially open to students and staff last week, with the main build having commenced in September 2018 and our first mechanical installation in May 2019.